A selection of recent work. Further case studies covering offshore, distilling, food manufacturing, wastewater and data centre projects are available on request.

Client: UK refinery and fuels terminal operator
Programme value: ~£50m
Project period: 2024-26
Setting: live COMAH site
Following the end of refining operations in 2025, the site had to be converted into a refined fuels import terminal. The work ran on a live, safety-critical COMAH site while redundant refinery plant was decommissioned and demolished at the same time.
Embedded project management · Owner-side engineering · Contract team leadership · CDM 2015
Sustained owner-side project leadership on a complex brownfield site where production, construction and demolition all run at the same time.

Client: UK biodiesel producer
Scope: operating projects, mothballing and decommissioning
Role: CDM Principal Designer
Regulators: SEPA / APHA
The work built on first-hand knowledge of the plant, gained delivering process and plant improvement projects on the site while it was in full production.
When biodiesel production ceased, the owner needed the process plant held safely and compliantly while the future of the site was decided. It then needed a full decontamination and decommissioning strategy taken to the market.
Operating plant projects · Fractional project management · Owner-side engineering · CDM Principal Designer · Tender management
Continuity from an operating biofuels plant to decommissioning: project delivery while the site ran, then regulatory, maintenance and commercial responsibility held for an owner with no remaining site team.
We will send a short selection that matches the work you have in mind.
Manero Engineering Services